Thursday, November 20, 2008

Lots and lots of wood

The framing started a little later than we would have hoped.  The foundation took a few extra days, so where our plumber had been scheduled for monday with tuesday inspection.  The rain caused it to be install on Friday with inspection on the following Monday.  That would have left the copper exposed over the weekend and well, we weren't having that.  So, almost a week late, the foundation was finished.

But framing moved ridiculously quick.  This was after only one day.

After two days.
After four days.
And they would have finished on the fifth day, but they ran out of the techshield roofing material.